Audit Analysis
The Guyuan 30.6 MW wind project is a CDM avoidance-type project with a jurisdictional baseline and VVB-confirmed additionality, but it carries moderate data-reliability concerns from a contradiction in claimed ER figures across two monitoring reports and an unusual ratio where verified ERs (44,567) far exceed the claimed figure (12,207). Two material findings and the absence of a formal Letter of Approval from the Chinese DNA at the time of the monitoring report introduce compliance uncertainty. Overall the project is structurally sound for a wind-avoidance credit but the ERR discrepancy warrants caution before relying on the verified figure.
Red Flags
- Contradiction in claimed ERs: 12,207 (monitoring report, 2012-12-31) vs 15,891 (monitoring report, 2012-11-01) — the more recent figure is privileged but the 31% gap signals internal inconsistency in the project's reporting.
- Verified ERs (44,567) are approximately 3.6× the claimed ERs (12,207) for what appears to be the same monitoring window, an unusual inversion that raises over-crediting or scope-mismatch questions.
- Corrective action noted: the project had not yet obtained the formal Letter of Approval (LoA) from the Chinese DNA at the time of the December 2012 monitoring report.
- Two material findings in the verification: Shandong Province omitted from the NCPG baseline boundary, and insufficient detail on NCV, oxidation factors, and baseline assumptions in the OM/BM.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2008 | 58,316 | 0 | 58,316 | |
| 2009 | 44,565 | 0 | 44,565 | |
| 2011 | 44,623 | 0 | 44,623 | |
| 2012 | 163,557 | 0 | 163,557 | |
| 2013 | 28,100 | 0 | 28,100 | |
| Total | 339,161 | 0 | 339,161 |
Risk Indicators
VVB-confirmed combined test
Avoidance project, no reversal risk
0% justified as negligible for wind
Jurisdictional grid EF baseline
Safeguards mentioned, FPIC/grievance not documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →