Hamal Solar Power Project

GS-1631 ↗ · current registry ID: GS6414

#1377of 1935 in Renewable energy#252of 295 in Turkey#1248of 1801 in Gold Standard (GS)#446of 806 in AMS-I.D

4.6/ 10
Integrity
5.5
Transparency
4.0
Claim Safety
4.5
Documentation
3.5

Audit Analysis

The Hamal Solar Power Project is a Gold Standard solar thermal electricity project in Turkey with a verified combined additionality test and a jurisdictional baseline, but it is undermined by an extensive list of over 50 corrective actions, multiple contradictions between verification reports issued just days apart, and a low extraction confidence rating. The project was retroactively registered from CDM, and while the claimed and verified emission reductions match at 18,098 tCO₂e, a parallel report from eight days earlier states only 9,501 tCO₂e, raising material concerns about calculation reliability.

Red Flags

  • Two verification reports issued eight days apart (2025-12-10 and 2025-12-18) report materially different verified ERR values (9,501 vs 18,098 tCO₂e) and different grid emission factors (0.5676 vs 0.6488), indicating unresolved calculation or scope discrepancies.
  • Over 50 corrective actions were issued by the VVB, including errors in emission factor values, ER calculations, monitoring period dates, and missing data in the ER calculation spreadsheet, signalling systemic MRV quality problems.
  • The project was originally a CDM project applying for retroactive Gold Standard registration, and the crediting period in the earlier report (2018–2023) is entirely different from the current period (2023–2028), suggesting a gap or overlap risk.
  • Minimum extraction confidence is rated low, meaning at least one key document was poorly readable, reducing reliability of the extracted data.

Credit Vintages

IssuedRetiredAvailable
2018
3,48503,485
2019
9,894829,812
2020
10,0714,3135,758
2021
10,0246,2353,789
2022
3,38703,387
Total36,86110,63026,231

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

low inherent reversal risk for solar electricity

Leakage

Deemed negligible; appropriate for grid-export solar

Baseline

Jurisdictional per 2025 report but contradicted by 2022 report

Safeguards

Grievance mechanism present; FPIC not conducted; benefit sharing described

Double-claim

CORSIA and CCP status not stated in available records

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-05AMS-I.D.

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents