Hamhung Hydropower Plant No.1
#1029of 1935 in Renewable energy#765of 1459 in CDM (UNFCCC)#330of 806 in AMS-I.D
Audit Analysis
A small hydro project in North Korea validated under CDM with a VVB-confirmed investment additionality test, but the record is undermined by four cross-document contradictions (baseline method, leakage justification, ERR figures, crediting period), 13 material findings with no recorded corrective actions, and the absence of a verified ERR figure. The physical nature of the hydro infrastructure limits permanence and greenwashing risk, yet the data-quality issues and missing safeguards documentation prevent a higher rating.
Red Flags
- Two monitoring reports report materially different claimed ERR values (68,555 in the April 2017 report vs 23,547 in the May 2018 report) with no verified figure available to reconcile them
- 13 material findings (CAR01–CAR10, CL01–CL03) were raised during verification, including missing investment-analysis parameters and a generator-type inconsistency, yet no corrective actions are recorded as required
- Baseline method is stated as 'jurisdictional' in the 2012 validation report but 'project' in the 2018 monitoring report, creating ambiguity about the actual baseline construction
- Grid emission factor of 0.8833 tCO₂/MWh is dated 2011 but applied to a 2017–2018 monitoring period, a seven-year gap with no updated factor documented
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2017 | 68,554 | 0 | 68,554 | |
| Total | 68,554 | 0 | 68,554 |
Risk Indicators
VVB-confirmed investment test
low inherent risk for hydro
0% deduction with contradictory justifications
Method contradicts across documents; jurisdictional per vali
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →