Hangtian Wanyuan Gaizhou Xutun Wind Farm Project
#1030of 1935 in Renewable energy#570of 1084 in China#766of 1459 in CDM (UNFCCC)#811of 1287 in ACM0002
Audit Analysis
A CDM wind farm project with a VVB-confirmed investment additionality test and a standard jurisdictional grid baseline, but the record is heavily weighted toward validation-stage documents with nine material findings, no monitoring or verification data, and two inter-document contradictions on leakage treatment and additionality test type. The absence of any verified emission reduction figures or monitoring period data significantly limits confidence in the project's actual performance.
Red Flags
- Nine material findings (CARs/CLs) at validation, including incomplete common-practice analysis for similar wind projects in Liaoning Province (CAR B4) and calculation errors in the emission reduction spreadsheet (CAR B5), indicating a weak initial PDD
- No monitoring period, verified ERR, or verification report found in the extracted record despite the crediting period (2013–2019) having fully elapsed
- Contradiction between the validation report (leakage 'deemed negligible') and the PDD (leakage 'quantified') creates ambiguity about the actual leakage treatment
- Contradiction between the validation report (additionality test: investment) and the PDD (additionality test: combined) raises questions about which test was actually applied
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed but PDD contradiction and incomplete common-pr
Operational wind; no reversal risk identified
0% deduction, 'deemed negligible' but contradicted by PDD
Jurisdictional grid EF (0.963575, 2009), standard for CDM wi
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →