Hangzhou Huadian Banshan Power Generation Co., Ltd.s Natural Gas Power Generation Project
#24of 1329 in Industrial#76of 1084 in China#136of 1459 in CDM (UNFCCC)#2of 19 in AM0029
Audit Analysis
A CDM fossil-fuel-switch project (coal-to-natural-gas) with a well-supported additionality case (combined test, IRR below benchmark, VVB-confirmed) and inherently low permanence risk. However, several key MRV parameters (FNRB, usage monitoring method, usage rates) are absent from the extracted record, and four inter-document contradictions—two of which are genuine—introduce moderate uncertainty around baseline methodology and leakage treatment.
Red Flags
- Baseline method is described as 'project-specific' in the monitoring report but 'jurisdictional' in the PDD; the discrepancy is unresolved in the available documents.
- Grid emission factor is from 2006 and no updated or reassessed baseline value is found in any document.
- FNRB value, usage monitoring method, and usage rates are all absent from the extracted record, limiting independent verification of the claimed reductions.
- CORSIA eligibility and CCP status are not stated in any available document, leaving dual-channel risk unassessed.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2011 | 269,646 | 0 | 269,646 | |
| 2012 | 1,187,378 | 0 | 1,187,378 | |
| 2013 | 718,041 | 0 | 718,041 | |
| Total | 2,175,065 | 0 | 2,175,065 |
Risk Indicators
VVB-confirmed combined test, IRR below benchmark
Fossil fuel switch, no reversal risk inherent
0% deduction, quantified justification (fuel switch)
Project-specific, grid EF from 2006, method contradiction
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →