Hasanbeyli 50 MW WPP, Turkey
GS-117 ↗ · current registry ID: GS1190
#81of 295 in Turkey#162of 1801 in Gold Standard (GS)#277of 1287 in ACM0002
Audit Analysis
The Hasanbeyli 50 MW wind project is a standard grid-displacement wind project under Gold Standard with a confirmed investment additionality test and a jurisdictional grid emission factor baseline. Inherent permanence risk is minimal for wind, and the 0% leakage deduction is reasonable given the project type. However, low extraction confidence, numerous corrective action requests across verification cycles, and several unquantified fields in the monitoring record limit confidence in the overall data quality.
Red Flags
- Low extraction confidence across the document set indicates at least one key document was poorly readable, reducing reliability of extracted figures
- 48+ Corrective Action Requests and 1 Forward Action Request across multiple verification cycles suggest recurring documentation and reporting deficiencies
- The 2022 verification report does not explicitly address reversal/permanence risk, and no buffer pool percentage is stated in the extracted record
- Grid emission factor of 0.6482 tCO2/kWh is from 2018 and has not been updated in the available documents for the 2024 monitoring period
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2014 | 70,309 | 56,383 | 13,926 | |
| 2015 | 89,921 | 89,921 | 0 | |
| 2016 | 78,038 | 78,038 | 0 | |
| 2017 | 86,947 | 77,170 | 9,777 | |
| 2018 | 102,941 | 35,696 | 67,245 | |
| 2019 | 97,151 | 36,776 | 60,375 | |
| 2020 | 98,660 | 54,318 | 44,342 | |
| 2021 | 104,009 | 95,266 | 8,743 | |
| 2022 | 95,234 | 79,978 | 15,256 | |
| 2023 | 9,251 | 0 | 9,251 | |
| Total | 832,461 | 603,546 | 228,915 |
Risk Indicators
Investment test, VVB-confirmed
Wind project, no storage risk
0% deduction, justified as negligible
Jurisdictional grid EF (2018)
FPIC, grievance mechanism, benefit sharing documented
CORSIA/CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →