Hebei Bodeyulong Phase Three 49.5 MW Wind Farm
#505of 1935 in Renewable energy#211of 1084 in China#330of 1459 in CDM (UNFCCC)#377of 1287 in ACM0002
Audit Analysis
A 49.5 MW onshore wind farm under CDM with a VVB-confirmed investment additionality test and no inherent permanence risk, but the record is weakened by an internal contradiction in reported emissions reductions, a financial calculation error flagged as a corrective action, and inconsistent baseline and leakage characterisations across documents. The project is fundamentally low-risk in design (wind displacement of grid electricity) yet the documentation gaps and data inconsistencies prevent a higher confidence rating.
Red Flags
- Internal contradiction within the same monitoring report: two different total ERR figures (379,850 and 35,847) appear for the same field, creating uncertainty about the actual verified reduction volume.
- Corrective Action 02 identifies an incorrect income-tax calculation in the IRR spreadsheet (negative values in the first two years), which directly undermines the investment-test additionality claim.
- Baseline method is described as 'project-specific' in the 2016 monitoring report but 'jurisdictional' in the 2012 validation report, raising questions about which baseline was actually applied.
- Verified ERR for the monitoring period (2013–2016) is not found in the extracted record, preventing an independent cross-check of claimed reductions.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2016 | 375,904 | 0 | 375,904 | |
| Total | 375,904 | 0 | 375,904 |
Risk Indicators
VVB-confirmed investment test
Wind project – no reversal risk
0% deduction, justified for grid displacement
Method label inconsistent across documents; grid EF from 200
Safeguards and benefit-sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →