Hebei Guyuan Huanghualiang Windfarm Project
#176of 1084 in China#288of 1459 in CDM (UNFCCC)#330of 1287 in ACM0002
Audit Analysis
A CDM wind project in China with VVB-confirmed additionality and appropriate treatment of leakage and permanence, but undermined by three material findings (meter calibration non-compliance, sensitivity analysis inconsistency, and an unsubstantiated tariff assumption) and a notable 32% decline in verified emissions reductions between the first and second monitoring periods. The project is fundamentally low-risk in design (wind displacing grid electricity) but the data quality issues and contradictions across documents introduce moderate uncertainty.
Red Flags
- Material finding CL-6: the project used a tariff of 0.54 RMB/kWh while the highest applicable tariff was 0.65 RMB/kWh, undermining the investment additionality case
- Material finding CL-5: sensitivity analysis results in the PDD were inconsistent with the IRR spreadsheet, indicating internal data quality problems
- Verified emissions reductions dropped from 85,533 tCO2 (first monitoring period, 12 months) to 58,411 tCO2 (second period, 10 months), a ~18% per-month decline that may signal over-crediting in the original PDD estimate
- Contradiction in baseline method: the validation report describes a jurisdictional baseline while the monitoring report describes a project-specific baseline
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2012 | 85,428 | 0 | 85,428 | |
| 2013 | 58,430 | 0 | 58,430 | |
| Total | 143,858 | 0 | 143,858 |
Risk Indicators
VVB-confirmed combined test
Avoidance project, no reversal risk
0% justified for grid-displacement wind
Method contradiction; 2009 grid EF
Mentioned but no FPIC or grievance detail
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →