Hebei Shangyi Dongshan Wind Farm Project
#774of 1935 in Renewable energy#386of 1084 in China#553of 1459 in CDM (UNFCCC)#603of 1287 in ACM0002
Audit Analysis
A CDM wind energy project in China with a jurisdictional grid baseline and a VVB-validated ERR of 94,634 tCO₂e over a 7-year crediting period. The project benefits from the inherent permanence of wind (no reversal risk) and a reasonable 0% leakage deduction, but the extracted record lacks explicit additionality test details and a monitoring period, and a significant discrepancy between the PDD and validation report on the claimed ERR raises documentation consistency concerns.
Red Flags
- The PDD (Aug 2019) states a total ERR of 662,438 tCO₂e while the validation report (Sep 2019) validates only 94,634 tCO₂e — a roughly 7-fold discrepancy that, although resolved in favour of the lower VVB figure, indicates a material inconsistency in the project's foundational documents.
- Additionality test type and VVB confirmation of additionality are not captured in the extracted record, leaving a gap in verifying a mandatory CDM requirement.
- Monitoring period is not stated in any available document, limiting the ability to assess MRV cadence and data currency.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2013 | 36,685 | 0 | 36,685 | |
| 2019 | 526,919 | 0 | 526,919 | |
| Total | 563,604 | 0 | 563,604 |
Risk Indicators
Test not explicitly captured in record
Avoidance project, no reversal risk
0% deemed negligible, reasonable for wind
Jurisdictional grid EF, reassessed 2019
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →