Hebei Weichang Dishuihu Wind Power Project
#313of 1935 in Renewable energy#120of 1084 in China#203of 1459 in CDM (UNFCCC)#234of 1287 in ACM0002
Audit Analysis
A CDM wind power project in China with confirmed additionality (combined test, VVB-verified) and inherently low permanence risk as an avoidance-type project. The first monitoring period delivered only ~28% of the pro-rata lifetime expectation, which is conservative but raises questions about the ex-ante estimate. Several documentation gaps and contradictions between the validation and monitoring reports (leakage justification, baseline method, crediting period dates) moderate confidence in the overall record.
Red Flags
- Contradiction between validation report (leakage 'deemed negligible') and monitoring report (leakage 'quantified') while the deduction remains 0% — the justification basis is inconsistent across documents
- Grid emission factor fixed at 0.9502 tCO₂/MWh from 2009 with no evidence of periodic update over the 7-year crediting period
- Eight material findings (CAR01–03, CL01–05) in the validation report, including missing DNA approval letters, incomplete PDD parameters, and an opaque IRR calculation
- Baseline method described as 'project' in the monitoring report but 'jurisdictional' in the validation report — the applicable baseline approach is ambiguous
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2012 | 30,544 | 0 | 30,544 | |
| 2013 | 98,708 | 0 | 98,708 | |
| Total | 129,252 | 0 | 129,252 |
Risk Indicators
Combined test, VVB-confirmed
Avoidance project, no reversals
0% deduction, contradictory justification
Grid EF 2009, method ambiguous across docs
Mentioned but FPIC/grievance not detailed
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →