Hebei Weichang Miaozigou 49.5MW Wind Farm Project
#1380of 1935 in Renewable energy#840of 1084 in China#1114of 1459 in CDM (UNFCCC)#1064of 1287 in ACM0002
Audit Analysis
A 49.5 MW onshore wind farm in Hebei, China, validated under CDM with a combined additionality test confirmed by DNV. The project design is technically straightforward, but the available record is limited to the validation stage: no monitoring or verification data, low extraction confidence, and eight clarifications plus two corrective actions in the validation report weaken confidence in the additionality case and overall data reliability.
Red Flags
- Eight clarifications (CLs) in the validation report question the additionality benchmark (8% IRR), investment cost assumptions, sensitivity analysis, and monitoring equipment accuracy — the additionality case required substantial justification before VVB sign-off.
- Two corrective actions (CARs) were required: Letters of Approval from China and the Annex I party, and the Memorandum of Consent, were not provided at validation.
- No monitoring or verification reports were found in the extracted record; actual performance against the claimed 98,081 tCO₂e/year (686,567 tCO₂e over the 7-year crediting period) cannot be confirmed.
- Minimum extraction confidence is rated low, indicating at least one key document was poorly readable, reducing reliability of the extracted data.
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed but 8 CLs on IRR benchmark and cost assumption
mixed evidence / unresolved risk
0 % deduction, deemed negligible — consistent with wind disp
Jurisdictional grid EF (0.8958, 2012), standard for Chinese
Safeguards and benefit-sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →