Hebei Weichang Zhangjiawan Wind Power Project
#860of 1935 in Renewable energy#449of 1084 in China#614of 1459 in CDM (UNFCCC)#674of 1287 in ACM0002
Audit Analysis
A CDM wind power project in China verified by Bureau Veritas with a combined additionality test, but the verification surfaced a below-benchmark IRR (6.63% vs 8%), meter accuracy deficiencies, and 18 corrective actions. The project is an avoidance-type (grid displacement) with no reversal risk, and the first monitoring period delivered roughly 72% of the pro-rata expectation, which is conservative. Multiple contradictions between the PDD, validation report, and monitoring report reduce confidence in the consistency of the project record.
Red Flags
- IRR of 6.63% falls below the 8% benchmark cited in the validation report, raising questions about the robustness of the additionality claim despite VVB sign-off
- Meter accuracy for the backup line (1.0) and 35 kV lines (0.5S) is lower than the 0.5 and 0.2S specified in the registered PDD, requiring a 1.005 correction factor and a meter replacement
- Five contradictions across documents (leakage justification, additionality test type, baseline method, ERR figures, crediting period) indicate inconsistent project documentation
- 18 corrective actions were required at validation, including IRR calculation inconsistencies, missing stakeholder engagement details, and PDD-IRR spreadsheet discrepancies
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2012 | 95,937 | 0 | 95,937 | |
| 2013 | 87,693 | 0 | 87,693 | |
| Total | 183,630 | 0 | 183,630 |
Risk Indicators
VVB-confirmed but IRR below 8% benchmark
Avoidance project, no reversal risk
0% deduction, justified per methodology but docs inconsisten
Grid EF stated, but method contradicts across docs
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →