Hebei Yuxian Yongshengzhuang 49.5 MW Wind Power Project
#508of 1935 in Renewable energy#216of 1084 in China#334of 1459 in CDM (UNFCCC)#381of 1287 in ACM0002
Audit Analysis
A 49.5 MW onshore wind project in Hebei, China, validated under CDM methodology ACM0002 v20.0 by Applus+ (LGAI). The jurisdictional baseline and negligible-leakage assumption are standard and defensible for wind, but the available record contains only a validation report and PDD — no monitoring report — so actual performance against the 569,359 tCO₂e ex-ante estimate cannot be independently confirmed.
Red Flags
- No monitoring report found in the extracted record; the 'verified' ERR figure (569,359) is identical to the claimed figure and appears to be the ex-ante validation estimate rather than a measured result
- Additionality test type and VVB confirmation are not captured in the extracted data, leaving the specific additionality basis unconfirmed
- CORSIA eligibility and CCP status are not stated in any available document, leaving dual-channel risk unassessed
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
Validation report exists but specific test type not captured
Wind generation – minimal reversal risk
0 % deduction, justified as negligible for grid-connected wi
Jurisdictional grid EF (2017), reassessed 2020
Safeguards and benefit-sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →