Heilongjiang Beiantun 49.5MW Wind Power Project
#1117of 1935 in Renewable energy#628of 1084 in China#852of 1459 in CDM (UNFCCC)#872of 1287 in ACM0002
Audit Analysis
A 49.5 MW onshore wind project in Heilongjiang, China, registered under CDM with a jurisdictional baseline and a 7-year crediting period. The project is fundamentally low-risk in design (wind displacing grid electricity, negligible leakage), but the extracted record lacks an explicit additionality assessment and contains a significant discrepancy between the PDD's ex-ante estimate (602,511 tCO₂e) and the validation report's validated figure (86,073 tCO₂e), creating uncertainty about the true credit volume.
Red Flags
- ERR contradiction: the PDD (Oct 2019) states a total of 602,511 tCO₂e while the validation report (Oct 2019) validates only 86,073 tCO₂e — a 7× difference that is not explained in the extracted record
- Additionality test type and VVB confirmation are not found in the extracted record, a mandatory element under CDM rules
- Material finding CAR-1: the monitoring plan in PDD v04 was inconsistent with the actual situation and the approved revised monitoring plan, requiring a PDD revision
- One of the four evidence documents is of unknown type, reducing confidence in the completeness of the documentation set
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2009 | 71,967 | 0 | 71,967 | |
| 2011 | 99,531 | 0 | 99,531 | |
| 2012 | 258,943 | 0 | 258,943 | |
| Total | 430,441 | 0 | 430,441 |
Risk Indicators
Not found in extracted record; likely in PDD but unconfirmed
Avoidance project; no reversal risk
0% with 'deemed negligible' justification; appropriate for w
Jurisdictional grid EF (0.9139, 2019); reassessed 2019
Mentioned but no FPIC or grievance mechanism details found
CORSIA and CCP status not stated; dual-channel risk unassess
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.