Heilongjiang Fujin 48MW Wind Power Project

CDM-8820 ↗

#225of 1935 in Renewable energy#80of 1084 in China#140of 1459 in CDM (UNFCCC)#162of 1287 in ACM0002

6.3/ 10
Integrity
6.8
Transparency
5.2
Claim Safety
6.5
Documentation
6.8

Audit Analysis

A 48 MW onshore wind project in Heilongjiang, China, registered under CDM with a combined additionality test confirmed by VVB TOY NORD. The project's avoidance-based design (displacing grid electricity) carries low permanence risk, and the 0% leakage deduction is reasonable for wind. However, a contradiction in the baseline method description between the PDD and the monitoring report, combined with the absence of a verified ERR figure, limits confidence in the credit quantity.

Red Flags

  • Baseline method is described as 'project' in the 2022 monitoring report but 'jurisdictional' in the 2012 PDD — an unresolved inconsistency that could affect the validity of the emission factor applied.
  • No verified ERR figure was found in any available document, making it impossible to confirm actual delivery against the 729,140 tCO₂e lifetime claim.
  • Five material findings were raised during validation (missing host-country approval, turbine type inconsistency, methodology version, threshold analysis, crediting start date); all were subsequently resolved, but the cluster of issues suggests initial documentation quality was below standard.

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

Avoidance project, no reversal risk

Leakage

0% deemed negligible, appropriate for wind

Baseline

Method contradiction between PDD and MR

Safeguards

Mentioned but FPIC/grievance not detailed

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-31ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents