Heilongjiang Hailin Weihushan Wind Power Project
#510of 1935 in Renewable energy#218of 1084 in China#336of 1459 in CDM (UNFCCC)#383of 1287 in ACM0002
Audit Analysis
A CDM wind power project in China with a well-supported additionality case (combined test confirmed by TÜV Rheinland, IRR below benchmark without CERs) and a standard jurisdictional baseline using the Combined Margin of NEPG. However, the available record lacks any monitoring-period data, verified emission reductions, or safeguards detail, and the low extraction confidence limits assurance. The project is a straightforward avoidance-type wind installation with minimal permanence or leakage risk, but the evidentiary base is thin.
Red Flags
- ERR figures differ by a factor of seven between the PDD (850,332 tCO₂e) and the validation report (121,476 tCO₂e); although likely an annual-versus-lifetime basis difference, the discrepancy is not explicitly reconciled in the documents
- No monitoring-period data or verified emission reductions are present in the extracted record, leaving actual delivery unconfirmed
- Minimum extraction confidence is rated low, meaning at least one key document was poorly readable and the full evidentiary picture may be incomplete
- Crediting-period start and end dates differ by two months between the PDD (Dec 2011 – Nov 2018) and the validation report (Oct 2011 – Sep 2018)
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed combined test; IRR below benchmark without CER
Avoidance project; no reversal risk inherent to wind generat
0% deduction justified by ACM0002; appropriate for grid disp
Jurisdictional CM of NEPG; standard for onshore wind in Chin
Safeguards and benefit-sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →