Heilongjiang Huanan Hengdaishan West Wind Power Project
#775of 1935 in Renewable energy#387of 1084 in China#462of 1339 in Verra (VCS)#604of 1287 in ACM0002
Audit Analysis
A registered VCS wind power project in China with a VVB-confirmed investment additionality test and no material findings, but undermined by a project-specific baseline, a grid emission factor drawn from 2004 (nearly two decades old at verification), and a 0% leakage deduction with no stated justification. Multiple contradictions across documents—particularly on baseline method and leakage treatment—reduce confidence in the data record.
Red Flags
- Grid emission factor of 1.1014 tCO₂/MWh is from 2004, nearly 18 years before the 2022 verification report; China's grid mix has changed substantially since then, creating a material over-crediting risk.
- Leakage deduction is 0% and the verification report states leakage was 'not addressed,' while the 2022 monitoring report claims it was 'quantified'—an unresolved contradiction that leaves the leakage treatment unclear.
- Baseline method is recorded as 'project' in the verification report but 'jurisdictional' in the 2022 monitoring report; the project-specific baseline is the weaker of the two and is the value in the authoritative verification document.
- FPIC was not conducted and no grievance mechanism is in place, despite safeguards being mentioned in the verification report.
Credit Vintages Exhausted
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2008 | 25,946 | 25,946 | 0 | |
| 2009 | 8,347 | 8,347 | 0 | |
| Total | 34,293 | 34,293 | 0 |
Risk Indicators
VVB-confirmed investment test
Avoidance project, no reversal risk
0% deduction, no justification in verification report
Project-specific baseline, 2004 grid EF
Mentioned but no FPIC or grievance mechanism
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →