Heilongjiang Qianjin Biomass Power Generation Project

CDM-4053 ↗

#200of 352 in Biomass#938of 1084 in China#1254of 1459 in CDM (UNFCCC)#30of 81 in ACM0006

4.3/ 10
Integrity
5.5
Transparency
3.8
Claim Safety
3.5
Documentation
3.8

Audit Analysis

A CDM biomass power generation project with VVB-confirmed additionality but significant data reliability concerns, including a seven-fold discrepancy between the PDD and validation report on expected emissions reductions, contradictory leakage and baseline characterisations, and no verified monitoring data available. The project's avoidance-type design limits reversal risk, but the absence of a buffer pool, quantified leakage treatment, and low document extraction confidence undermine confidence in the credit claims.

Red Flags

  • Seven-fold discrepancy in expected emissions reductions: the PDD (Sep 2010) states 994,133 tCO2e while the validation report (Oct 2010) confirms only 142,019 tCO2e, a ratio of approximately 7:1 that is not explained in the available documents
  • Leakage justification is contradictory: the validation report states leakage is 'deemed negligible' (0% deduction) while an appendix describes it as 'quantified', leaving unclear whether a substantive leakage analysis was performed
  • Baseline method is contradictory: the validation report characterises it as 'project-specific' while an appendix references a 'jurisdictional' baseline, creating ambiguity about the actual baseline construction
  • No verified emissions reduction data (total ERR verified) is available for the 2011–2017 monitoring period, preventing any assessment of actual delivery versus claims
  • Minimum extraction confidence is rated low, indicating at least one key document was poorly readable and the extracted facts may be incomplete

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

mixed evidence / unresolved risk

Leakage

0% deduction, contradictory justification

Baseline

Project-specific, method contradicted in appendix

Safeguards

Mentioned, benefit sharing described, FPIC/grievance not sta

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-31ACM0006

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents