Heilongjiang Yilan Chenguang Wind Power Project
#1034of 1935 in Renewable energy#573of 1084 in China#770of 1459 in CDM (UNFCCC)#815of 1287 in ACM0002
Audit Analysis
A CDM wind power project in China validated by CCSC with a jurisdictional baseline and a 7-year crediting period. The core design is sound for a renewable energy avoidance project, but the extracted record lacks explicit additionality documentation, contains a significant discrepancy between the PDD and validation report on total emissions reductions, and carries a material finding requiring a PDD revision. Overall a moderate-quality project with identifiable gaps in the available evidence.
Red Flags
- The PDD (2019-08-27) states a total ex-ante estimate of 735,693 tCO2e while the validation report (2019-08-28) and monitoring report both state 105,099 tCO2e — a roughly 7-fold discrepancy that is not explained in the available documents.
- Additionality test type and VVB confirmation of additionality are not stated in any extracted document, despite additionality being a core CDM requirement.
- A material finding (CAR-1) was raised regarding inconsistency of the EGfacility,y description with ACM0002 v19.0, with a corrective action still required to revise the PDD.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2013 | 92,990 | 0 | 92,990 | |
| Total | 92,990 | 0 | 92,990 |
Risk Indicators
Test type not stated in extracted record
Avoidance project, no reversal risk
0% deemed negligible, appropriate for wind
Jurisdictional, grid EF 0.9139 (2019)
Mentioned and benefit sharing described, FPIC/grievance not
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →