Heilongjiang Yilan Yunling Wind Power Project
#863of 1935 in Renewable energy#452of 1084 in China#617of 1459 in CDM (UNFCCC)#677of 1287 in ACM0002
Audit Analysis
A CDM wind power project in China with a VVB-confirmed combined additionality test and an appropriate grid-based baseline, but undermined by four material findings requiring corrective action in the PDD's financial analysis, a leakage assessment that was ultimately not addressed, and a significant discrepancy between the ex-ante ERR estimate (119,838 tCO₂e) and the figure reported in the monitoring period (75,112 tCO₂e). The project is inherently low-risk for reversal given its avoidance nature, but documentation gaps and unresolved contradictions limit confidence in the credit quantity.
Red Flags
- Four material findings (CARs) in the validation report indicate errors in the PDD's financial analysis, including an incorrect emission factor tool version, a misdescription of electricity imports between grid regions, an omitted interest component in the IRR calculation, and an operating cost inconsistency with the approved FSR
- Leakage justification is recorded as 'not addressed' in the later monitoring report (June 2013), contradicting an earlier monitoring report (August 2012) that described it as 'quantified' — the 0% leakage deduction lacks a documented rationale
- The total ERR claimed differs substantially between the validation report (119,838 tCO₂e) and the monitoring report (75,112 tCO₂e), a discrepancy of roughly 37% that is not explained in the available documents
- No verified ERR figure (total_err_verified) was found in any available document, making it impossible to confirm actual delivery against the ex-ante estimate
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2013 | 109,918 | 0 | 109,918 | |
| Total | 109,918 | 0 | 109,918 |
Risk Indicators
VVB-confirmed but 4 CARs in financial analysis
Avoidance project, no reversal risk
0% deduction, justification not addressed
Jurisdictional grid baseline, appropriate for wind
Safeguards mentioned, FPIC and grievance mechanism not docum
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →