Hongyan 8MW Hydropower Project in Luoping County
#1179of 1935 in Renewable energy#692of 1084 in China#906of 1459 in CDM (UNFCCC)#380of 806 in AMS-I.D
Audit Analysis
The Hongyan 8 MW hydropower project is a CDM avoidance project with VVB-confirmed additionality and no inherent reversal risk, but its credibility is undermined by eleven material findings at validation, a 37 % discrepancy in the grid emission factor between the validation report and an appendix, and a contradiction in the stated baseline method. No monitoring-period data or verified emission reductions are available in the extracted record, leaving the actual delivery of the 167,454 tCO₂e lifetime claim unassessable.
Red Flags
- Grid emission factor differs by 37 % between the validation report (0.7134 tCO₂/MWh, 2010) and an appendix (0.976 tCO₂/MWh); the higher value would inflate credits substantially
- Baseline method is stated as 'project' in the validation report but 'jurisdictional' in the PDD, creating ambiguity about which baseline was actually used
- Eleven material findings at validation include non-reproducible investment sensitivity calculations, missing financial parameters, and insufficient monitoring-system description
- No monitoring-period data, verified ERR, or FNRB method is present in the extracted record, so actual credit delivery cannot be verified
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
Avoidance project, no reversal risk
0 % deemed negligible; appendix inconsistency
Project-specific; PDD contradiction; no reassessment data
Safeguards mentioned; no FPIC or grievance detail
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →