Huadian Daan Fengshuishan Phase II Wind Farm Project
#1265of 1935 in Renewable energy#762of 1084 in China#999of 1459 in CDM (UNFCCC)#983of 1287 in ACM0002
Audit Analysis
A CDM wind farm project with solid additionality (combined test verified by DNV) and a standard jurisdictional grid-emission-factor baseline, but severely limited by the absence of any monitoring data, a seven-fold discrepancy between the PDD and validation report on total emissions reductions, and multiple unresolved material findings at validation. The project's inherent low reversal risk as a wind avoidance project is a positive, but the data gaps and ERR inconsistency materially weaken confidence in the credit quantity.
Red Flags
- Total ERR in the PDD (721,742 tCO₂e) is approximately 7× the figure in the validation report (103,106 tCO₂e); both documents are from August 2012 and should be on the same basis, indicating a serious data-reliability problem.
- No monitoring reports, verified ERR, or monitoring period are present in the extracted record, leaving the actual delivery of credits entirely unverified.
- Five material findings were raised at validation (missing approval letters, tariff source, investment/O&M cost justification, meter accuracy, stakeholder consultation sufficiency), and corrective actions including PDD revision were required.
- Leakage justification is inconsistent across documents: the validation report states 'deemed negligible' while an earlier document references a 'quantified' approach.
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
Combined test, VVB-verified (DNV)
Wind avoidance – low inherent reversal risk
0% deduction, reasonable for grid-connected wind
Jurisdictional grid EF (1.0103, 2012)
Safeguards mentioned; FPIC and grievance mechanism not docum
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →