Huadian Gansu Akesai Dangjinshan First Phase 49.5MW Wind Power Project
#1124of 1935 in Renewable energy#638of 1084 in China#862of 1459 in CDM (UNFCCC)#877of 1287 in ACM0002
Audit Analysis
A 49.5 MW onshore wind project in Gansu, China, validated under CDM methodology ACM0002 with a jurisdictional grid baseline and VVB-confirmed investment additionality. The project's core design is sound for wind, but the validation report carried 13 material findings (including multiple corrective-action requests on additionality benchmarks, IRR transparency, and monitoring plan gaps), and no verified emission-reduction figures or monitoring reports were found in the extracted record. Safeguards documentation is thin, with no FPIC or grievance mechanism identified.
Red Flags
- 13 material findings in the validation report, including 7 corrective-action requests covering additionality benchmark clarity, IRR parameter transparency, and missing monitoring parameters for grid electricity
- No verified emission-reduction figures found in any extracted document; the 652,778 tCO2e figure is ex-ante only
- Grid emission factor of 0.918 tCO2/MWh is anchored to 2008 data with no stated baseline reassessment date
- No FPIC, grievance mechanism, or detailed safeguards documentation identified in the extracted record
- Contradiction between the validation report (leakage 'deemed negligible') and an appendix (leakage 'quantified')
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
Wind generation – low reversal risk
0% deduction justified, but record contradiction
Jurisdictional grid EF (2008), no reassessment date
Mentioned but no FPIC or grievance mechanism found
CORSIA and CCP status both unstated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →