Huadian Haiyuan Wuyuan Second Phase 49.5MW Wind Power Project
#1125of 1935 in Renewable energy#639of 1084 in China#863of 1459 in CDM (UNFCCC)#878of 1287 in ACM0002
Audit Analysis
A 49.5 MW onshore wind project in China under CDM with a standard methodology (ACM0002) and VVB-confirmed additionality, but the available record is limited to a 2012 validation report and PDD with no monitoring data, a significant ERR figure discrepancy between documents, and 18 corrective actions flagged by the VVB. The project's low inherent risk (grid-displacement wind) is offset by the absence of any verified emissions data and low document extraction confidence.
Red Flags
- ERR figure discrepancy: the PDD (Nov 2012) reports 562,471 tCO₂e while the validation report (Dec 2012) reports 80,353 tCO₂e — a 7× difference that, while likely reflecting a lifetime-vs-annual basis, is not explicitly reconciled in the documents
- 18 corrective actions were raised by TÜV SÜD in the validation report, covering additionality justification, IRR methodology, bank contract verification, and PDD completeness — indicating a weak initial submission
- No monitoring reports, verified ERR, or usage monitoring method are present in the extracted record, making it impossible to confirm actual delivery against the ex-ante estimate
- Minimum extraction confidence is rated low, meaning at least one key document was poorly readable and critical data may be missing
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
Combined test, VVB-confirmed
mixed evidence / unresolved risk
0% deemed negligible, appropriate for grid wind
Jurisdictional grid EF, standard for wind
Mentioned but no FPIC or grievance mechanism documented
CORSIA and CCP status not stated in record
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →