Huadian Kailu Yihetala Phase Two 49.5 MW Wind Farm Project in China
#186of 1935 in Renewable energy#60of 1084 in China#113of 1459 in CDM (UNFCCC)#131of 1287 in ACM0002
Audit Analysis
A 49.5 MW onshore wind project under CDM with a combined additionality test confirmed by DNV and no material findings. The project-specific baseline and unresolved contradictions between the validation and monitoring reports (baseline method, ERR figures, crediting period dates) introduce moderate uncertainty, while the absence of a verified ERR figure prevents a definitive over- or under-delivery assessment.
Red Flags
- Baseline method is stated as 'project-specific' in the monitoring report but 'jurisdictional' in the validation report — an unresolved contradiction that affects the credibility of the counterfactual
- Total ERR claimed (131,370 tCO2e) exceeds the validation report's ex-ante estimate (113,255 tCO2e) by ~16%, and no verified ERR figure is available to confirm actual delivery
- Crediting period start date differs between documents (2010-10-30 in monitoring report vs 2010-08-01 in validation report), creating ambiguity about the exact baseline period
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
Combined test, VVB-confirmed
Avoidance project, no reversal risk
0% deduction, quantified as negligible
Project-specific, cross-doc contradiction
Mentioned, benefit sharing present, FPIC/grievance not stated
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →