Huadian Kulun 201MW Wind Farm Project
#269of 1935 in Renewable energy#103of 1084 in China#170of 1459 in CDM (UNFCCC)#199of 1287 in ACM0002
Audit Analysis
A 201 MW onshore wind project under CDM with a VVB-confirmed investment additionality test and a conservative ex-ante emission estimate that the first monitoring period substantially exceeded. The project is free of inherent reversal risk (avoidance-type), but documentation gaps (no verified ERR figure, no fnrb data, CDM-era reporting) and a baseline-method contradiction between the validation and monitoring reports limit confidence. Overall a solid but mid-tier credit with no critical red flags.
Red Flags
- Baseline method is stated as 'project-specific' in the monitoring report but 'jurisdictional' in the validation report — an unresolved contradiction that affects baseline credibility
- No verified ERR figure is available in the extracted record; only the claimed figure (245,259 tCO₂) from the monitoring report is present
- Leakage justification is inconsistent: the monitoring report says 'quantified' while the validation report says 'deemed negligible', both yielding a 0% deduction
- No verification report appears in the evidence document list; only a validation report and a single monitoring report are available
- CORSIA eligibility and CCP status are not stated in any available document, leaving dual-channel risk unassessed
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2011 | 246,053 | 0 | 246,053 | |
| Total | 246,053 | 0 | 246,053 |
Risk Indicators
VVB-confirmed investment test
Avoidance-type, no reversal risk
0% deduction, inconsistent justification
Project-specific, method contradicts across docs
Mentioned but FPIC and grievance not documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →