Huadian Ningxia Ningdong Yangjiayao Phase III Wind Farm Project

CDM-5102 ↗

#1126of 1935 in Renewable energy#640of 1084 in China#864of 1459 in CDM (UNFCCC)#879of 1287 in ACM0002

5.0/ 10
Integrity
6.5
Transparency
3.0
Claim Safety
5.0
Documentation
4.5

Audit Analysis

A CDM wind farm project in China with a VVB-confirmed combined additionality test and a standard jurisdictional grid-emission-factor baseline. The fundamental design is sound for a wind project, but the available record contains only a validation report with no monitoring or verification data, and a ten-fold discrepancy in the claimed emission reduction between the PDD and the validation report undermines confidence in the credit quantity.

Red Flags

  • The PDD states a total emission reduction of 948,700 tCO2e while the validation report (later, VVB-verified) states 94,870 tCO2e — a ten-fold discrepancy that has not been reconciled in the available record.
  • No monitoring reports or verification reports were found in the extracted record, so actual generation and credit issuance over the 2011–2021 crediting period cannot be confirmed.
  • CORSIA eligibility and CCP status are not stated in any available document, leaving dual-channel or double-claiming risk unassessed.

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

Avoidance project, no reversal risk

Leakage

Negligible, grid-exported power

Baseline

Jurisdictional grid EF, standard method

Safeguards

Mentioned but FPIC and grievance mechanism not documented

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-04ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents