Inner Mongolia Jingneng Saihan Wind Farm Phase II Project

VCS-921 ↗

5.9 / 10
Integrity
5.6
Transparency
6.2
Claim Safety
5.4
Documentation
7.1

Score Breakdown

Integrity

verified Additionality is confirmed by the VVB in the validation documentation, and no material findings are reported.

missing Leakage is set at 0% but leakage is not addressed in the monitoring report, and baseline reassessment timing is not stated in the extracted record.

Transparency

verified A named VVB (Applus+ Certification) and a clearly stated monitoring period (2009-10-27 to 2015-09-20) support traceability.

missing Key figures and narratives conflict across documents (ER totals, leakage treatment, safeguards), reducing MRV clarity.

Claim Safety

verified The project is explicitly not CORSIA-eligible, lowering aviation-claim channel risk.

missing Over-crediting/greenwashing risk is elevated by contradictions in ER totals and unclear leakage justification despite a 0% deduction.

Documentation

verified A relatively large document set is referenced (14 documents across PDD, validation, monitoring, issuance) with high extraction confidence.

missing Corrective action requests in the monitoring documentation indicate documentation/template non-conformance that should have been resolved.

Detailed Analysis

Integrity

The validation documentation confirms additionality, and the project applies ACM0002 with a project-specific baseline approach, which is typical for grid-connected wind. However, the monitoring report records a leakage deduction of 0% while also not addressing leakage, weakening the integrity of the emissions accounting. Baseline reassessment timing is not stated in the extracted record, and the presence of corrective actions suggests process weaknesses even if no material findings were reported.

Transparency

The monitoring report provides a defined monitoring period (2009-10-27 to 2015-09-20) and identifies the VVB as LGAI Technological Center, S.A. (Applus+ Certification), which supports auditability. Still, transparency is undermined by inconsistent reporting across the PDD/validation/monitoring documents on core items (ER totals, leakage narrative, safeguards). The fact that verified ERs are higher than claimed ERs further reduces clarity on what was actually asserted versus checked.

Claim Safety

The project is explicitly not CORSIA-eligible, which reduces the risk of high-profile aviation claims. Nonetheless, claim safety is weakened by contradictions in emissions reduction totals and by the mismatch between a 0% leakage deduction and inconsistent leakage treatment between the validation report and monitoring report. CCP status is not stated in the extracted record, leaving uncertainty about alignment with higher-integrity labels.

Documentation

Documentation coverage is relatively strong with multiple document types (PDD, validation report, monitoring report, issuance) and a high extraction confidence, which supports a higher documentation score. However, the monitoring documentation includes a corrective action requesting revision of the VCS project description to the most updated requirements and template, indicating documentation quality issues. Several key fields (e.g., buffer pool, baseline reassessment timing) are not found in the extracted record, limiting completeness.

Overall

I privileged the more recent monitoring/validation documents (2021) over the older PDD (2012) for ER totals, but the fact that the validation report’s claimed ERs (379,769) conflict with the PDD (182,099) and the verified ERs are even higher (395,987) indicates a serious consistency problem that lowers confidence. For leakage, I treated the monitoring report’s statement that leakage was not addressed as controlling for transparency/integrity because it reflects what was actually reported during monitoring, even though the validation report says leakage was quantified; this inconsistency warrants a downward adjustment. For safeguards/FPIC/grievance/benefit-sharing, I accepted that these were present per the 2021 monitoring report but scored down because the earlier validation report indicates they were absent, suggesting evolving or inconsistently documented safeguards. Finally, the crediting period conflict (monitoring report: 2009-2019 vs later validation report: 2019-2029) is unresolved in the extracted record and materially affects interpretation of eligibility windows, so overall confidence is moderated.

Audit Analysis

This is a VCS wind power project using ACM0002 with additionality confirmed by the VVB and no material findings reported, which supports basic credibility. However, multiple cross-document inconsistencies (including claimed vs verified ERs, leakage treatment, safeguards, and even the crediting period) raise reliability and over-crediting concerns and reduce confidence in the record.

Project Description

The Beijing International New Energy Co., Ltd. invested in a project in Suniteyouqi, Xilinguole League, Inner Mongolia Autonomous Region, P.R. China that involved installing 24 wind turbines with a total capacity of 48 MW. Each turbine had a capacity of 2000 kW.

Red Flags

  • Verified ERs exceed claimed ERs (395,987 vs 379,769), indicating internal inconsistency in reported results
  • Leakage is recorded as 0% but the monitoring report does not address leakage while the validation report says it was quantified
  • Safeguards/FPIC/grievance and benefit-sharing are inconsistently reported across documents
  • Crediting period dates conflict between the monitoring report and a later validation report, creating uncertainty about the applicable crediting window

Credit Vintages

Issued Retired Available
2010
84,031 0 84,031
2011
49,809 0 49,809
2012
47,718 0 47,718
2013
78,997 10,555 68,442
2014
79,635 79,635 0
2015
79,562 78,249 1,313
2017
1,092 1,030 62
2020
120,794 120,778 16
Total 541,638 290,247 251,391

Cosa migliorerebbe questo punteggio

  • Provide a reconciled ER table (claimed vs verified vs issued) with clear references and explanations for why verified ERs exceed claimed ERs.
  • Clarify leakage treatment under ACM0002 for this project and align the monitoring report narrative with the validation approach (or apply a justified deduction).
  • Resolve and document the correct crediting period dates with registry evidence and update all public-facing documents accordingly.

Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.

Risk Indicators

Additionality

VVB-confirmed additionality

Permanence

Avoidance project (no reversal pool needed)

Leakage

0% leakage with inconsistent justification

Baseline

Project-specific baseline; reassessment timing unclear

Safeguards

Safeguards/FPIC reported but inconsistent across docs

Double-claim

Not CORSIA-eligible; CCP status not stated

Where to buy

Marketplaces

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis Provenance Scored 2026-04-02 General Methodology v2.0 Documentazione completa

Sei il proprietario di questo progetto?

Correzione metadati (gratuita)

Nome, paese, marketplace o link errati? Segnalacelo.

Non modifica lo score.

[email protected]

Rivalutazione con nuovi documenti

Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.

Invia Documenti