Karaburun Wind Power Plant (Phase-II)

ICR-88 ↗

#1439of 1935 in Renewable energy#32of 75 in TR#60of 154 in Intl. Carbon Registry (ICR)#1104of 1287 in ACM0002

4.5/ 10
Integrity
5.0
Transparency
4.5
Claim Safety
4.5
Documentation
3.5

Audit Analysis

The Karaburun Wind Power Plant (Phase-II) is a grid-connected wind project under the ICR standard with VVB-confirmed additionality, but the validation process surfaced 39 corrective action requests and multiple inter-document contradictions (FPIC status, baseline method, grid emission factor) that undermine confidence in the underlying data. The project delivers exactly 100% of its pro-rata ex-ante expectation for the elapsed period, which is reassuring, yet the absence of a buffer pool, unaddressed reversal risk, and CORSIA eligibility without a clear CCP status create moderate over-crediting and permanence concerns.

Red Flags

  • 39 Corrective Action Requests and 1 Forward Action Request were issued during validation, including substantive issues with the additionality common-practice threshold (PDD used >2 where the Tool requires >3) and double-counting clarification
  • FPIC status is contradictory: the PDD (Sep 2024) states FPIC was conducted, while the validation report (Nov 2024) records it as not conducted
  • No buffer pool is in place for a 10-year crediting period and reversal risk is marked as 'not addressed' despite a risk assessment identifying Turkey's economic instability
  • CORSIA eligibility is confirmed but CCP status is not stated, creating dual-channel / double-claim ambiguity
  • Baseline method is contradictory within the validation report itself: 'project' (Nov 2024) vs 'jurisdictional' (Oct 2024), and the grid emission factor differs between documents (0.6488 vs 0.7424)

Credit Vintages

IssuedRetiredAvailable
2019
146,3620146,362
2020
298,4480298,448
2021
298,4480298,448
2022
298,4480298,448
2023
298,4480298,448
2024
298,4480298,448
2025
298,4480298,448
2026
298,4480298,448
2027
298,4480298,448
2028
298,4480298,448
2029
152,0860152,086
Total2,984,48002,984,480

Risk Indicators

Additionality

VVB-confirmed but threshold error and 39 CARs

Permanence

reversal risk not addressed

Leakage

0% deduction, negligible for grid-connected wind

Baseline

Project-specific; method and grid EF contradictory

Safeguards

Grievance mechanism present; FPIC status contradictory

Double-claim

CORSIA-eligible; CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-08ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents