Killik Wind Power Plant

GS-1269 ↗ · current registry ID: GS947

#622of 1935 in Renewable energy#127of 295 in Turkey#325of 1801 in Gold Standard (GS)#480of 1287 in ACM0002

5.6/ 10
Integrity
6.0
Transparency
5.5
Claim Safety
5.5
Documentation
5.0

Audit Analysis

The Killik Wind Power Plant is a Gold Standard wind project in Turkey with VVB-confirmed additionality and a reasonable zero-leakage justification for a grid-displacement technology. However, multiple contradictions across documents—particularly on baseline method, grid emission factor, and additionality test type—undermine data reliability, and the project's CORSIA eligibility combined with an unclarified CCP status introduces dual-channel risk. The low extraction confidence and a high volume of corrective actions during verification further temper confidence in the project's documentation quality.

Red Flags

  • Seven contradictions identified across documents, including conflicting baseline methods (project vs. jurisdictional), grid emission factors (0.6482 vs. 0.7258), and additionality test types (combined vs. investment), indicating data reliability issues
  • CORSIA eligibility confirmed while CCP status is not mentioned in any available document, creating unresolved dual-channel risk
  • 16 Corrective Action Requests and 24 Clarification Requests were issued during verification, with several relating to stakeholder engagement gaps (low women's participation, incomplete evaluation forms)
  • Minimum extraction confidence rated low, meaning at least one key document was poorly readable, reducing assurance in the extracted data
  • Grid emission factor sourced from 2018 and contradicted by a higher value (0.7258) in the monitoring report, raising questions about which parameter drives credit calculations

Credit Vintages

IssuedRetiredAvailable
2011
8,3058,3050
2012
61,75661,643113
2013
66,29566,2950
2016
17,04817,0480
2017
58,33457,0081,326
2018
45,48545,4850
2021
15,501015,501
2022
55,956055,956
2023
14,426014,426
Total343,106255,78487,322

Risk Indicators

Additionality

Combined test, VVB-confirmed

Permanence

Avoidance type, no reversal events

Leakage

0% with negligible justification

Baseline

Method and grid EF contradictions

Safeguards

FPIC and grievance present, engagement gaps

Double-claim

CORSIA eligible, CCP unclarified

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-05ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents