Skip to main content
GSSmall, Low - Impact HydroTurkeyACM0002

Kusakli Hydro Electric Power Plant

GS-10 ↗ · current registry ID: GS1014

#82of 295 in Turkey#165of 1801 in Gold Standard (GS)#291of 1287 in ACM0002

6.0/ 10
Integrity
6.5
Transparency
5.5
Claim Safety
6.0
Documentation
5.5

Audit Analysis

The Kusakli Hydro Electric Power Plant is a small run-of-river hydro project in Turkey that displaces grid electricity, with additionality confirmed by the VVB via an investment test and a reasonable 0% leakage deduction. However, a contradiction between the verification report (project-specific baseline) and the PDD (jurisdictional baseline), the absence of a buffer pool, and 24 corrective actions raised during verification introduce moderate concerns about baseline robustness and documentation quality. The project delivered approximately 85% of its pro-rata annual expectation for the 2024 monitoring period, indicating no obvious over-crediting.

Red Flags

  • Baseline method contradiction: the verification report (2024) states a project-specific baseline while the PDD (2023) references a jurisdictional baseline — the basis for calculating reductions is ambiguous
  • 24 corrective actions were required during verification, indicating significant documentation and methodological gaps in the PDD and monitoring procedures
  • No buffer pool is in place to cover potential reversals, although reversal risk is low for an avoidance-type hydro project
  • Total verified ERR is not stated in the extracted record, leaving the independently confirmed reduction figure unclear

Credit Vintages

IssuedRetiredAvailable
2019
5,65805,658
2020
15,223015,223
Total20,881020,881

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project, no reversals

Leakage

0% with negligible justification

Baseline

Project-specific, method contradiction

Safeguards

FPIC, grievance, benefit sharing

Double-claim

CORSIA/CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-05ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents