ORTAMANDIRA WPP

GS-368 ↗ · current registry ID: GS2468

#238of 295 in Turkey#1088of 1801 in Gold Standard (GS)#991of 1287 in ACM0002

4.8/ 10
Integrity
5.0
Transparency
5.5
Claim Safety
4.5
Documentation
4.0

Audit Analysis

The Ortamandira Wind Power Plant is a Gold Standard wind avoidance project with confirmed additionality and a recent 2024 verification, but it is undermined by a very high volume of corrective actions (18 CARs, 29 open items), nine cross-document contradictions, and a project-specific baseline. The verified emissions reductions (10,931 tCO₂e) represent roughly half the pro-rata expectation for the monitoring year, which is conservative but raises questions about the accuracy of the ex-ante estimate.

Red Flags

  • 18 Corrective Action Requests and 29 corrective action items across the verification cycle indicate systemic data-quality and reporting deficiencies
  • Two verification reports (Aug 2024 vs Sep 2024) report materially different verified ERR figures (41,835 vs 10,931 tCO₂e) and different crediting periods (2022–2029 vs 2015–2022), creating uncertainty about which figure is authoritative
  • Leakage justification is contradictory: the 2024 verification report labels it 'quantified' while the 2020 PDD states 'deemed negligible,' yet the actual deduction is 0%
  • Baseline method is contradictory: the 2024 verification report classifies it as 'project' while the 2020 PDD classifies it as 'jurisdictional'
  • Crediting period dates conflict between two verification reports issued weeks apart (2015–2022 vs 2022–2029), making it unclear which period the 2024 monitoring falls under

Credit Vintages

IssuedRetiredAvailable
2015
13,03813,0380
2016
21,99021,542448
2017
20,38820,3880
2018
10,66710,6670
2019
21,93921,9390
2020
22,55222,5520
2021
22,17321,785388
2022
25,54225,5420
2023
23,12220,4852,637
2024
1,3611,3610
Total182,772179,2993,473

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project, no reversal risk

Leakage

0% deduction, contradictory justification

Baseline

Project-specific, reassessed 2022

Safeguards

Mentioned but logbook gaps noted

Double-claim

CCP and CORSIA status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-05ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents