Pamir I Hydropower Generation

VCS-98 ↗

#1186of 1935 in Renewable energy#808of 1339 in Verra (VCS)#383of 806 in AMS-I.D

4.9/ 10
Integrity
5.5
Transparency
4.5
Claim Safety
5.0
Documentation
4.0

Audit Analysis

The Pamir I Hydropower project is a small-scale renewable energy avoidance project with VVB-confirmed additionality and a jurisdictional grid baseline, but it carries significant integrity concerns from a load-shifting rule breach, unaddressed leakage, and multiple material findings including catastrophic flooding damage. The project delivered roughly 60% of its PDD-estimated reductions, which is conservative, yet the load-shifting exception and inconsistent documentation across reports undermine confidence in the validity of all issued credits.

Red Flags

  • Load shifting threshold was exceeded during Unit 2 rehabilitation and the applicable rule was not applied, raising the risk that some claimed credits represent shifted rather than genuinely displaced grid electricity
  • Leakage deduction is 0% with the justification recorded as 'not addressed' in the 2016 verification report, despite the 2012 report having stated it was 'quantified' — an unexplained regression in rigor
  • Line meters EL1 and EL2 were never installed as proposed in the monitoring plan; the deviation was approved by the DOE but the measurement basis for energy output is therefore weaker than designed
  • Safeguards documentation is inconsistent: the 2007 validation report mentions safeguards, but the 2014 verification report does not; FPIC was not conducted and no grievance mechanism is in place
  • Min extraction confidence is rated low, indicating at least one key document was poorly readable, reducing reliability of the extracted record

Credit Vintages

IssuedRetiredAvailable
2005
3,1273,1270
2006
17,74917,7490
2007
25,70825,7080
2008
37,88937,8890
2009
34,55234,5520
2010
73,09973,0990
2012
27,99927,9990
2013
38,26637,1311,135
2014
31,78610,44921,337
2015
25,378025,378
Total315,553267,70347,850

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

Avoidance project, no reversal risk

Leakage

0% deduction, justification not addressed

Baseline

Jurisdictional but contradicted in monitoring report

Safeguards

No FPIC, no grievance mechanism, inconsistent documentation

Double-claim

CORSIA excluded, CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-03AMS-I.D

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents