Proyecto Hidroeléctrico Alejandría
#881of 1935 in Renewable energy#39of 124 in Colombia#35of 99 in CerCarbono (CC)#694of 1287 in ACM0002
Audit Analysis
The Alejandría hydroelectric project is a well-understood avoidance mechanism (grid-displacing renewable generation) with VVB-confirmed additionality and inherent permanence, but it is undermined by a heavy burden of 19 material findings, 18 corrective actions, and nine cross-document contradictions that raise questions about data reliability. The verified ERR matches the claimed figure exactly and the pro-rata delivery sits at roughly 85% of the lifetime expectation, which is conservative. Overall the project is credible in concept but its documentation record is weak and the low extraction confidence limits assurance.
Red Flags
- Nineteen material findings and eighteen corrective actions were raised during validation/monitoring, including incorrect turbine capacity (7.5 MW vs 7.689 MW), wrong environmental license (PCH Nare instead of PCH Alejandría), and missing RENARE registration — all closed but indicative of a weak initial submission
- Baseline method is stated as 'jurisdictional' in the monitoring report but 'project' in the validation report; leakage justification is 'deemed negligible' in the monitoring report but 'quantified' in the validation report — unresolved contradictions in core MRV parameters
- FPIC is recorded as conducted in the monitoring report but not conducted in the PDD, creating uncertainty about the timing and scope of free, prior and informed consent
- Minimum extraction confidence is rated low, meaning at least one key document was poorly readable, reducing assurance over the extracted figures
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2016 | 4,062 | 4,062 | 0 | |
| 2017 | 28,381 | 28,381 | 0 | |
| 2018 | 37,867 | 37,867 | 0 | |
| 2019 | 34,987 | 34,987 | 0 | |
| 2020 | 41,821 | 41,821 | 0 | |
| 2021 | 46,697 | 46,619 | 78 | |
| 2022 | 39,809 | 35,310 | 4,499 | |
| 2023 | 44,005 | 0 | 44,005 | |
| 2024 | 42,742 | 0 | 42,742 | |
| 2025 | 17,426 | 0 | 17,426 | |
| Total | 337,797 | 229,047 | 108,750 |
Risk Indicators
VVB-confirmed barrier test
Avoidance project, no reversal risk
0% deduction, justification contradicted across docs
Jurisdictional per MR, but VR says project-specific
FPIC contradiction; grievance mechanism present
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →