Audit Analysis
A teak reforestation project in Campeche and Tabasco, Mexico, with a confirmed additionality test and a substantial 31% buffer pool, but undermined by 20 material findings in the 2025 verification report involving formula errors, calculation mistakes, and a missing leakage term. The project-specific baseline, unaddressed leakage justification, and potentially overdue baseline reassessment (10-year mark passed in 2023) create meaningful integrity and over-crediting risks that the buffer pool only partially offsets.
Red Flags
- 20 material findings in the 2025 verification report include formula errors in carbon estimation sheets, incorrect Rj value application, area data mismatch between spreadsheet and PDD, and a missing leakage term in column AT formulas — all pointing to systematic calculation weaknesses
- Leakage deduction is 0% with the justification recorded as 'not addressed' in the 2025 verification report, contradicting the 2018 verification report which stated it was 'deemed negligible'; for a reforestation project displacing citrus agriculture, zero leakage with no quantified justification is a significant gap
- Baseline reassessment appears overdue: the project started in June 2013, making the 10-year VCS ALM reassessment due by mid-2023, yet no reassessment date is recorded in any available document as of the February 2025 verification
- 12 corrective actions were required by the VVB, including updating carbon estimation formulas, correcting citrus baseline discounting, and providing ownership evidence for each project instance
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2013 | 15,589 | 12,258 | 3,331 | |
| 2016 | 50,519 | 50,519 | 0 | |
| 2017 | 50,519 | 50,519 | 0 | |
| 2018 | 118,057 | 113,057 | 5,000 | |
| 2019 | 74,318 | 74,318 | 0 | |
| 2020 | 121,675 | 116,675 | 5,000 | |
| 2021 | 105,101 | 1,839 | 103,262 | |
| 2022 | 144,871 | 3,500 | 141,371 | |
| Total | 680,649 | 422,685 | 257,964 |
Risk Indicators
VVB-confirmed combined test
31% buffer pool, no reversals
0% deduction, justification not addressed
Project-specific, reassessment overdue
FPIC and grievance per 2025 VR, earlier docs inconsistent
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →