VCS avoidance India Registry: Registered Documentazione completa General Methodology v2.0

Renewable Energy Project By LNB Group

VCS-1418 ↗

5.1 / 10
Integrity
6.1
Transparency
4.8
Claim Safety
5.0
Documentation
3.6

Score Breakdown

Integrity

verified Additionality was confirmed by the VVB through an investment test in the verification report.

missing Leakage is not addressed, with a stated leakage deduction of 0% and no justification provided.

Transparency

verified The latest verification report shows claimed and verified emissions reductions both at 44,129, which supports internal consistency for the current period.

missing The monitoring report evidence appears incomplete, with missing meter specifications, calibration records, and some supporting invoices/JMRs noted in corrective action requests.

Claim Safety

verified The project is an avoidance project under ACM0002 with a recent baseline reassessment in 2024, which is better than an undated project-specific baseline.

missing The project is not CORSIA-eligible, while CCP status is not stated, and leakage treatment is weak because the report gives no justification for the zero deduction.

Documentation

verified A large number of documents were used, and the verification report includes a long list of corrective actions and clarifications that were reportedly closed.

missing Extraction confidence is low, and the record contains several contradictions on emissions reductions, crediting period, and safeguard-related items.

Detailed Analysis

Integrity

The verification report confirms additionality through an investment test and names VKU Certification Pvt. Ltd. as the VVB, which supports the project’s core integrity case. The project is an avoidance activity under ACM0002, and the baseline was reassessed in 2024, but leakage is weakly supported because the report gives a leakage deduction of 0% with no justification. No reversal events are reported, and as an avoidance project permanence risk is inherently limited, though the absence of a buffer pool value still leaves a documentation gap.

Transparency

The latest verification report shows claimed and verified emissions reductions both at 44,129 for the monitoring period from 2023-03-31 to 2024-09-30, which is a positive sign for internal consistency. However, the same report lists multiple corrective action requests about missing meter specifications, calibration evidence, voltage details, and supporting invoices/JMRs, indicating incomplete MRV transparency. The low extraction confidence further reduces confidence that all relevant disclosures were captured cleanly.

Claim Safety

Claim safety is moderate because the project uses a standard renewable energy methodology and the baseline was reassessed in 2024, which is preferable to an outdated or unstated baseline. That said, the report does not provide a leakage justification, and the project is explicitly not CORSIA-eligible, while CCP status is not stated. The contradiction history also shows earlier and later values for emissions reductions, which raises some over-crediting and version-control concerns even though the latest verification report is internally aligned.

Documentation

Documentation quality is limited by low extraction confidence and by the fact that the evidence document list is not informative in the extracted record. The verification report contains many corrective actions, including requests for updated templates, page numbers, audit history separation, calibration details, and no-double-accounting evidence, which suggests the file set was not fully complete at review time. Although the latest report appears to have closed several CARs and CLs, the contradictions on crediting period and safeguard-related disclosures indicate that the record is not fully stable across documents.

Overall

I privileged the latest verification report dated 2025-04-29 for the current emissions reduction figure of 44,129 because it is the most recent and specific source in the extracted record, even though earlier documents reported different values such as 59,776 and 74,871. I also privileged the latest safeguard-related disclosures where benefit sharing, grievance mechanism, and FPIC are marked true, but the contradiction log shows earlier documents saying otherwise, so reliability is reduced and the documentation score is pulled down. Because the project is registered and additionality is VVB-confirmed, the overall profile is not poor, but the missing monitoring evidence, weak leakage treatment, low extraction confidence, and multiple contradictions keep the assessment in the middle range.

Audit Analysis

This is a registered VCS renewable energy project with VVB-confirmed additionality and no reported reversal events, but the documentation quality is uneven and several verification requests remain unresolved in the extracted record. The project’s claimed and verified emissions reductions match in the latest verification report, yet missing monitoring details, low extraction confidence, and multiple document contradictions reduce confidence in the claim.

Project Description

This project involved the installation of Wind and Solar Power Projects across Rajasthan and Maharashtra in India. With a combined capacity of 27.20 MW, it includes 18 Wind Turbine Generators and 1 Solar power plant.

Red Flags

  • The verification report says key monitoring evidence was missing, including meter details, calibration support, and some electricity bills/JMRs.
  • There are contradictions across documents on emissions reductions, crediting period, and safeguard-related disclosures, which weakens reliability.

Credit Vintages

Issued Retired Available
2013
10,338 10,338 0
2014
33,421 33,421 0
2015
34,850 34,850 0
2016
41,690 41,690 0
2017
39,776 39,776 0
2019
13,421 13,421 0
2020
34,553 5,193 29,360
2021
30,416 769 29,647
2024
1,000 0 1,000
Total 239,465 179,458 60,007

Cosa migliorerebbe questo punteggio

  • Provide a complete, version-controlled monitoring package with meter specifications, calibration certificates, invoices/JMRs, and a clear audit trail for all reported reductions.
  • Resolve the document contradictions by publishing a reconciled emissions table, crediting-period history, and consistent safeguard disclosures across the monitoring and verification records.

Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project, no reversals reported

Leakage

Zero deduction without justification

Baseline

Project baseline, reassessed in 2024

Safeguards

FPIC and grievance mechanism present, but inconsistently doc

Double-claim

Not CORSIA-eligible; CCP status not stated

Where to buy

Marketplaces

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis Provenance Scored 2026-04-18 General Methodology v2.0 Documentazione completa

Sei il proprietario di questo progetto?

Correzione metadati (gratuita)

Nome, paese, marketplace o link errati? Segnalacelo.

Non modifica lo score.

[email protected]

Rivalutazione con nuovi documenti

Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.

Invia Documenti