Rio Negro Ceramic Fuel Switching Project
#725of 1329 in Industrial#116of 211 in Brazil#878of 1339 in Verra (VCS)#37of 60 in AMS-I.E
Audit Analysis
The Rio Negro Ceramic fuel-switching project has a sound core methodology (AMS-I.E.) with VVB-confirmed additionality and a quantified 5% leakage deduction, but is undermined by 12 cross-document contradictions—including a significant FNRB discrepancy (93.8 vs 0.8209)—14 corrective action requests, an expired clay extraction licence, and the absence of an environmental management system. The project is inherently low-risk on permanence (energy sector, no carbon storage), yet operational fragility (100% workforce turnover from flood losses) and a project-specific baseline that has not been reassessed introduce material uncertainty into the long-term credit validity.
Red Flags
- FNRB value contradicts between the 2024 verification report (93.8, national default) and the 2022 monitoring report (0.8209, local field), a discrepancy of roughly 14 percentage points that directly affects the ER calculation
- 14 Corrective Action Requests and 12 corrective actions were raised in the 2024 verification, including installation of a chimney filter, rebuilding of flood-damaged areas, and refurbishment of the Hoffman kiln—indicating significant operational non-conformities
- Clay extraction licence had expired at the time of verification, with renewal only 'requested', raising a legal-compliance risk for continued operation
- Workforce turnover surged from 45% to 100% due to flood losses, and no environmental management system is in place, signalling operational fragility
- FPIC was not conducted (per the 2024 verification report), despite a monitoring report from the same year claiming it was done—a direct contradiction on a VCS safeguard requirement
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2009 | 11,789 | 11,789 | 0 | |
| 2010 | 18,737 | 18,737 | 0 | |
| 2011 | 16,861 | 16,861 | 0 | |
| 2012 | 14,832 | 14,832 | 0 | |
| 2013 | 14,811 | 14,811 | 0 | |
| 2014 | 17,383 | 15,068 | 2,315 | |
| 2015 | 16,057 | 0 | 16,057 | |
| 2023 | 383 | 383 | 0 | |
| Total | 110,853 | 92,481 | 18,372 |
Risk Indicators
VVB-confirmed barrier test (2024)
Energy project – no storage, no reversal risk
5% quantified deduction applied
Project-specific; no reassessment date recorded
Grievance mechanism present; FPIC not conducted; no EMS
CORSIA excluded; CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →