Solar Power Project By TP Saurya Limited
#986of 1935 in Renewable energy#1of 9 in IN#26of 154 in Intl. Carbon Registry (ICR)#778of 1287 in ACM0002
Audit Analysis
A 10-year solar PV project in India with VVB-confirmed additionality and a jurisdictional baseline, but the verification report contains 28 material findings including inconsistencies in emission reduction values across documents, an unexplained gap between ex-ante and monitored ERs, and a double-counting flag in the verification summary table. The project type (solar) inherently carries low permanence and leakage risk, yet the volume of data-quality issues and missing information (FNRB, usage rates, CORSIA/CCP status) limits confidence in the credit's robustness.
Red Flags
- Verification report material finding states 'Double counting issuance and claiming is marked as yes' in the validation/verification summary table, though a corrective action suggests this may be a template misinterpretation by the VVB
- Inconsistencies in operating margin and capacity factor values between the ER sheet and PDDMR section 8.1.1, with no explanation provided for the difference between estimated and monitored ERs
- Section 10.5 reports 58,523 + 91,028 = 149,551 tCO2e for the monitoring period, while the verified total is 160,434 tCO2e — an unexplained gap of ~10,883 tCO2e
- Section 7.2 of the verification report states 58,232 tCO2e for Nov–Dec 2024, while PDDMR section 10.6 states 58,523 tCO2e for the same period
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2024 | 103,190 | 0 | 103,190 | |
| 2025 | 697,494 | 0 | 697,494 | |
| 2026 | 694,704 | 0 | 694,704 | |
| 2027 | 691,925 | 0 | 691,925 | |
| 2028 | 689,158 | 0 | 689,158 | |
| 2029 | 686,401 | 0 | 686,401 | |
| 2030 | 683,655 | 0 | 683,655 | |
| 2031 | 680,921 | 0 | 680,921 | |
| 2032 | 678,197 | 0 | 678,197 | |
| 2033 | 675,484 | 0 | 675,484 | |
| 2034 | 573,247 | 0 | 573,247 | |
| Total | 6,854,376 | 0 | 6,854,376 |
Risk Indicators
VVB-confirmed combined test
Solar project, no reversal risk
Deemed negligible, reasonable for solar
Jurisdictional, reassessment not yet due
Grievance mechanism present, FPIC not conducted
CORSIA/CCP status not stated; DC flag in report
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →