VCSEnergy industries (renewable/non-renewable sources)Cote D'Ivoire Registry: RegisteredACM0002

Soubre Hydropower Project

VCS-1522 ↗

#1281of 1935 in Renewable energy#883of 1339 in Verra (VCS)#995of 1287 in ACM0002

4.8/ 10
Integrity
5.5
Transparency
4.5
Claim Safety
5.0
Documentation
3.5

Audit Analysis

The Soubre Hydropower Project is a large-scale renewable energy project in Côte d'Ivoire with a fundamentally sound claim of displacing grid electricity. However, the project is undermined by a 23% exceedance of ex-ante emission reduction estimates, multiple unresolved corrective actions related to meter calibration, and significant contradictions between the verification and monitoring reports on additionality test type, baseline method, and ERR figures. The low extraction confidence and numerous incomplete documentation sections further erode confidence in the data quality.

Red Flags

  • Ex-post power generation and emission reductions exceed ex-ante estimates by 23%, flagged as a finding requiring VVB assessment but not yet resolved
  • Contradiction between verification report (investment test) and monitoring report (combined test) on additionality methodology
  • Contradiction between verification report (project-specific baseline) and monitoring report (jurisdictional baseline) on baseline method
  • ERR figures differ between the verification report (912,224 tCO2e) and the monitoring report (1,300,333 tCO2e), with unclear period attribution
  • Multiple incomplete PDD sections (Sections 1.10, 1.12.2, 1.12.3, 1.12.4) and missing legal declarations (non-rejection, non-claim) identified as CARs

Credit Vintages

IssuedRetiredAvailable
2017
376,96731,802345,165
2018
787,269149,236638,033
2019
959,44643,482915,964
2020
884,10160,263823,838
2021
691,737119,187572,550
2022
818,2030818,203
2023
449,6760449,676
Total4,967,399403,9704,563,429

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project, no reversal events

Leakage

0% with reasonable justification for displacement

Baseline

Project-specific baseline, reassessment timing not stated

Safeguards

FPIC, grievance mechanism, and safeguards documented

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-29ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents