Suloglu Wind Power Plant, Turkey

GS-493 ↗ · current registry ID: GS2763

#987of 1935 in Renewable energy#189of 295 in Turkey#639of 1801 in Gold Standard (GS)#779of 1287 in ACM0002

5.2/ 10
Integrity
4.5
Transparency
5.5
Claim Safety
6.0
Documentation
5.0

Audit Analysis

The Süloğlu Wind Power Plant is a Gold Standard wind project with a fundamentally sound design (grid-displacement avoidance, no reversal risk), but the verification record reveals extensive data-quality issues including generation-data discrepancies across multiple months, calculation errors, and QA/QC misalignment with the registered PDD. The project delivered roughly 72% of its pro-rata ex-ante expectation for the monitored period, which is conservative, yet the volume of material findings and corrective actions undermines confidence in the accuracy of the verified figures.

Red Flags

  • 25+ material findings in the 2025 verification report, including discrepancies in electricity generation data for at least six months (Nov 2016, Apr 2016, Sep/Oct/Nov 2015, Sep 2016) between the monitoring report and EPIAS/meter records
  • QA/QC procedures for the EGfacility,y parameter were not aligned with the registered PDD, and the project scenario criteria did not match methodology conditions
  • Additionality verification status is contradictory: the 2021 verification report confirms VVB verification, but the 2024 validation report records it as not verified
  • Leakage justification is recorded as 'not addressed' in the most recent verification report (2025), despite an earlier report (2021) indicating it was quantified
  • SDG Impact Tool was not applied to determine SDG impacts, a Gold Standard requirement

Credit Vintages

IssuedRetiredAvailable
2015
22,14522,1450
2016
115,906115,338568
2017
112,407112,4070
2018
126,227120,6475,580
2019
119,01138,09480,917
2020
124,4350124,435
2021
120,9320120,932
2022
42,25919,50822,751
Total783,322428,139355,183

Risk Indicators

Additionality

VVB-confirmed (2021) but contradicted by 2024 validation report

Permanence

Avoidance project, no reversal events

Leakage

0% deduction, justification not addressed in latest report

Baseline

Project-specific, reassessed 2024, PDD contradiction noted

Safeguards

Grievance mechanism and benefit sharing present, FPIC not conducted

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-06ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents