Taiping Township Waste Resource Utilization Project
#590of 1084 in China#680of 1339 in Verra (VCS)#10of 31 in ACM0022
Audit Analysis
The Taiping Township Waste Resource Utilization Project has VVB-confirmed additionality via an investment test and a consistent ERR estimate, but suffers from a project-specific modeled baseline, no stated buffer pool, three material findings with two corrective actions, and numerous missing operational parameters (FNRB, usage rates, feedstock sustainability). The project is in its early monitoring phase with a 10-year crediting period, and while no reversal events are expected, permanence safeguards are not explicitly documented.
Red Flags
- Three material findings in the validation report, including outdated grid emission factors and incomplete process diagrams, with two corrective actions still required
- Leakage justification is inconsistent between documents: the monitoring report states it was 'quantified' while the validation report characterises it as 'deemed negligible', yet the deduction is 0% in both cases
- Multiple critical operational parameters (FNRB, usage rates, energy source, feedstock sustainability, storage verification, LCA) are not stated in any available document
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
reversal deemed N/A
0% deduction; inconsistent justification across docs
Project-specific modeled baseline; no reassessment date
FPIC, grievance mechanism, benefit sharing documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →