Tayakadın Wind Power Project, Turkey
GS-2347 ↗ · current registry ID: GS7652
#399of 1935 in Renewable energy#87of 295 in Turkey#171of 1801 in Gold Standard (GS)#303of 1287 in ACM0002
Audit Analysis
The Tayakadın Wind Power Project is a straightforward renewable-energy avoidance project with VVB-confirmed additionality and no reported reversals, but it is undermined by a project-specific baseline, the absence of a stated buffer pool, and an unusually large number of corrective actions (over 30) that point to significant documentation-quality issues. ERR figures are internally consistent between the monitoring and verification reports for the current period, though a contradiction within the same monitoring report (130,832 vs 79,970 tCO₂e) raises a data-reliability flag. Overall the project is credible in concept but carries moderate execution and documentation risk.
Red Flags
- Over 30 corrective actions were required in the verification report, including typos in dates, inconsistent meter serial numbers, missing calibration evidence, and unresolved stakeholder-conflict clarifications — indicating weak internal quality control.
- A contradiction within the same monitoring report (dated 2025-12-05) shows two different claimed ERR values (130,832 and 79,970 tCO₂e), raising a data-integrity question that is not resolved in the verification report.
- The PDD dates from August 2017 while the grid emission factor was updated to a 2019 value; the baseline has not been formally reassessed in the extracted record, and the project-specific baseline method adds uncertainty relative to a jurisdictional baseline.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2021 | 33,996 | 0 | 33,996 | |
| 2022 | 84,673 | 1,520 | 83,153 | |
| 2023 | 92,646 | 28,227 | 64,419 | |
| 2024 | 79,970 | 14,718 | 65,252 | |
| 2025 | 7,434 | 7,095 | 339 | |
| Total | 298,719 | 51,560 | 247,159 |
Risk Indicators
VVB-confirmed investment test
no reversals
0% deduction, quantified justification
Project-specific, no reassessment date
Mentioned but inconsistently documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →