TCL Aobo (Tianjin) E-waste recycling and comprehensive utilization project(Phase II)
#531of 1084 in China#624of 1339 in Verra (VCS)#22of 72 in AMS-II.I
Audit Analysis
A VCS-registered e-waste recycling project in China with a VVB-confirmed investment additionality test and low permanence risk, but undermined by 16 material findings, 13 corrective actions, a project-specific baseline, a 0% leakage deduction with a thin 'deemed negligible' justification, and a confirmed absence of FPIC. The first monitoring period delivered roughly 87% of the pro-rata expectation, which is within a reasonable band but leaves modest over-crediting headroom unaddressed.
Red Flags
- 16 material findings and 13 corrective actions were raised during validation, including double-counting concerns on upstream/downstream processors, unclear hazardous-waste handling, and a missing demonstration of compliance with VCS Standard 4.7 requirement 2.1.3 (Excluded Project Activities).
- FPIC was not conducted according to the VVB's validation report, despite the PDD claiming otherwise; local informal waste collectors and recyclers were initially excluded from the local stakeholder consultation.
- Leakage deduction is 0% with a 'deemed negligible' justification in the validation report, which is a weak basis for an e-waste project operating in a market with active informal recycling channels.
- The quantity of metal and plastic recycled (Qi,y) was found to be inconsistent between the ER calculation spreadsheet and the Joint PD&MR, raising data-integrity concerns in the credit calculation.
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
Waste-handling; no reversal risk
0% deduction; 'deemed negligible' only
Project-specific; reassessment not yet due
Grievance present; FPIC not conducted
CORSIA & CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →