Tejuva-Chandgarh Wind Project
#321of 1935 in Renewable energy#169of 975 in India#163of 1339 in Verra (VCS)#243of 1287 in ACM0002
Audit Analysis
The Tejuva-Chandgarh Wind Project is a standard VCS renewable energy project (ACM0002 v17) with VVB-verified additionality and a jurisdictional grid baseline, presenting low inherent risk. However, the project record is marred by numerous documentation deficiencies (18 corrective actions, missing meter records, low extraction confidence) and the absence of FPIC, which temper an otherwise straightforward wind-energy credit.
Red Flags
- FPIC was not conducted despite the project operating in India, where community engagement is a recognized safeguard expectation
- Low extraction confidence across the document set, combined with 18 corrective action items and missing meter/invoice records, raises questions about the completeness of the underlying data
- Grid emission factor is from 2014; no evidence of a more recent update was found in the extracted record
- Benefit-sharing description is absent in the most recent monitoring report (2025), contradicting an earlier report that stated it was present
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2015 | 140,872 | 140,872 | 0 | |
| 2016 | 349,940 | 349,940 | 0 | |
| 2017 | 357,254 | 357,254 | 0 | |
| 2018 | 394,335 | 394,335 | 0 | |
| 2019 | 369,475 | 369,475 | 0 | |
| 2020 | 345,061 | 345,061 | 0 | |
| 2021 | 358,669 | 327,189 | 31,480 | |
| 2022 | 393,167 | 378,247 | 14,920 | |
| 2023 | 142,858 | 3,968 | 138,890 | |
| 2024 | 300,372 | 0 | 300,372 | |
| Total | 3,152,003 | 2,666,341 | 485,662 |
Risk Indicators
VVB-confirmed combined/investment test
Wind project – no reversal risk
0% deduction, reasonable for wind
Jurisdictional grid EF (0.99, 2014)
Grievance mechanism present; FPIC not conducted
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →