Umut-II Hydropower Plant, Turkey
#1193of 1935 in Renewable energy#225of 295 in Turkey#819of 1339 in Verra (VCS)#929of 1287 in ACM0002
Audit Analysis
The Umut-II Hydropower Plant is a VCS-registered renewable energy project with confirmed additionality and a jurisdictional baseline reassessed in 2024, but it delivered only 58% of its pro-rata expected reductions for the monitoring period due to seasonal water-flow variability. The verification process surfaced over 60 material findings and 12 corrective actions, and several contradictions between the PDD, validation report, and verification report undermine confidence in the data record.
Red Flags
- Verified reductions (115,715 tCO2e) are 49% below the ex-ante estimate for the same monitoring period (227,254 tCO2e), indicating the original projections were significantly overstated
- Over 60 material findings and 12 corrective actions were raised during verification, including discrepancies in electricity generation values between meter records and EPIAS records, and shared meters across Umut-I, II, and III requiring proportional allocation
- FPIC status is contradictory: the monitoring report states it was not conducted, while the PDD (2025) states it was conducted
- Grid emission factor differs between the PDD (0.4568 tCO2/MWh) and the verification report (0.551 tCO2/MWh), affecting the magnitude of claimed reductions
- CORSIA eligibility and CCP status are not stated in any available document, leaving dual-channel risk unassessed
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed combined test
Avoidance project, no reversal risk
0% justified as negligible for grid displacement
Jurisdictional, reassessed 2024
Grievance mechanism present; FPIC status contradictory
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →