Van Solar Power Project
#1048of 1935 in Renewable energy#203of 295 in Turkey#685of 1339 in Verra (VCS)#828of 1287 in ACM0002
Audit Analysis
The Van Solar Power Project is a registered VCS renewable energy project with confirmed additionality and no reversal events, but it carries moderate integrity and documentation concerns stemming from a project-specific baseline, a large volume of corrective actions (26 CARs, 14 CLs, 3 FARs at validation), and low extraction confidence across the document set. The ERR figures for the 2022–2024 monitoring period are internally consistent (claimed equals verified at 66,006 tCO₂e), and the 0% leakage deduction is reasonable for a solar PV project. Overall, the project is functional but its data quality and documentation depth fall short of best practice.
Red Flags
- 26 CARs, 14 CLs, and 3 FARs were raised during validation, indicating significant documentation and data-quality gaps at project inception
- Min extraction confidence is rated low, meaning at least one key document was poorly readable, undermining confidence in the extracted record
- Project-specific baseline method (not jurisdictional) with no stated baseline reassessment date, limiting baseline robustness
- Grid emission factor of 0.5676 tCO₂/MWh is from 2016 and may not reflect current Turkish grid conditions
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2018 | 4,618 | 0 | 4,618 | |
| 2019 | 30,315 | 0 | 30,315 | |
| 2020 | 35,754 | 0 | 35,754 | |
| 2021 | 38,015 | 0 | 38,015 | |
| 2022 | 35,919 | 0 | 35,919 | |
| 2023 | 36,480 | 0 | 36,480 | |
| 2024 | 6,940 | 0 | 6,940 | |
| Total | 188,041 | 0 | 188,041 |
Risk Indicators
VVB-confirmed investment test
Solar PV – no reversal risk, no events
0% deduction, quantified justification
Project-specific, no reassessment date
FPIC, grievance mechanism, safeguards documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →