Wind Energy Project By Ramco Group In India

VCS-669 ↗

#1195of 1935 in Renewable energy#621of 975 in India#821of 1339 in Verra (VCS)#931of 1287 in ACM0002

4.9/ 10
Integrity
4.5
Transparency
5.0
Claim Safety
5.5
Documentation
4.5

Audit Analysis

A wind energy avoidance project with a sound fundamental design (jurisdictional grid baseline, VVB-confirmed investment test, no permanence risk), but undermined by an unusually large volume of material findings (over 40 items) covering calibration gaps, meter-reading discrepancies, ownership mismatches, and a CDM/VCS double-counting concern. The project delivered approximately 98% of the pro-rata ex-ante expectation for the monitored period, and the registry's 'late to verify' status further erodes confidence in the MRV chain.

Red Flags

  • Over 40 material findings in the 2015 verification report, including double-counting of net energy from HTSC 1383 & 1384, uncalibrated meters (271 & 510), and missing calibration certificates for ELP 27 & 1532
  • CDM validation contract for a 41.6 MW portion was terminated, but the verification report requires re-verification of CDM status in every subsequent cycle to rule out double counting
  • Registry status is 'Late to verify', indicating a gap in the verification cadence expected under VCS rules
  • Multiple WTGs changed utility (grid export vs. captive) during the monitoring period, complicating the net-export calculation and requiring wheeling-charge and transmission-loss corrections that were initially omitted
  • Ownership of HTSC 973 attributed to Sri Ramco Spinners rather than the project proponent as stated in the PDD

Credit Vintages

IssuedRetiredAvailable
2006
106,84521,15785,688
2007
193,03741,681151,356
2008
309,581190,350119,231
2009
356,335356,3350
2010
320,210320,2100
2011
308,664308,6640
2012
319,205319,2050
2013
78,34677,556790
Total1,992,2231,635,158357,065

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project – no reversal risk

Leakage

0% deduction, deemed negligible for wind

Baseline

Jurisdictional grid EF (2008)

Safeguards

Mentioned but FPIC & grievance not detailed

Double-claim

CDM overlap flagged; CORSIA/CCP not stated

Where to buy

Marketplaces

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-04ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents