Wind energy project in different locations of India
#1500of 1935 in Renewable energy#825of 975 in India#1084of 1339 in Verra (VCS)#1147of 1287 in ACM0002
Audit Analysis
This multi-site Indian wind energy project (VCS-1526) is a registered VCS project with VVB-verified additionality and a jurisdictional baseline, but it suffers from a severe 81.6% installed-capacity reduction (119.55 MW to 22.05 MW) and delivered only about 49% of its revised ex-ante emission-reduction estimate for the monitoring period. Multiple material findings, four corrective-action requests, and significant documentation gaps in the monitoring report undermine confidence in the project's operational integrity, even though the under-delivery profile limits over-crediting risk.
Red Flags
- Installed capacity reduced by 81.6% (119.55 MW to 22.05 MW) due to WTG shutdowns and sales, constituting a major project-description deviation
- Verified ERR of 122,290 tCO2e is only ~9% of the pro-rata expectation derived from the original PDD lifetime estimate of 2,686,880 tCO2e, and ~49% of the revised ex-ante estimate of 247,634 tCO2e for the monitoring period
- Four corrective-action requests were raised covering project identification, VER estimation, and monitoring, plus additional VVB requirements for MR traceability and deviation assessment
- ERR sheet traceability is incomplete: total net generation cannot be traced to individual WTG generators
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-verified investment test, but contradicted by validation
inhere
0% deduction with quantified justification, appropriate for
Jurisdictional baseline per VR, but contradicted by validati
FPIC and grievance mechanism present, but benefit-sharing co
CORSIA eligibility and CCP status not stated in available do
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →