Wind Power Project in Rajasthan by LWEPL

VCS-1567 ↗

#635of 1935 in Renewable energy#312of 975 in India#373of 1339 in Verra (VCS)#493of 1287 in ACM0002

5.6/ 10
Integrity
5.5
Transparency
6.0
Claim Safety
6.0
Documentation
4.5

Audit Analysis

A 10-year VCS wind power project in Rajasthan with a jurisdictional grid baseline and VVB-confirmed combined additionality test. The fundamental credit logic is sound for a renewable energy displacement project, but the verification report surfaced over 20 material findings—including inconsistencies between the monitoring report narrative and the ER calculation sheet, missing meter calibration records, and absent commissioning certificates—indicating meaningful MRV data-quality gaps that temper confidence in the verified figures.

Red Flags

  • The verification report identifies that the total ER value in the monitoring report narrative is inconsistent with the ER calculation sheet, and the EG facility,y parameter shows the same discrepancy, raising data-integrity concerns for the 210,889 tCO2e verified figure.
  • Calibration certificates for energy meters covering the 2019–2022 monitoring period were not provided in the monitoring report, and the calibration frequency was not stated in the monitoring arrangement.
  • Commissioning certificates for all wind energy converters were not initially provided in the project design document and were flagged as a corrective action.
  • CORSIA eligibility and CCP status are not stated in any available document, leaving the double-claiming risk unassessed.

Credit Vintages Exhausted

IssuedRetiredAvailable
2014
12,86812,8680
2015
49,26149,2610
2016
53,32653,3260
2017
54,55354,5530
2018
51,18251,1820
2019
9,5989,5980
Total230,788230,7880

Risk Indicators

Additionality

Combined test, VVB-confirmed

Permanence

Non-AFOLU wind, no reversal risk

Leakage

0% justified for grid displacement

Baseline

Jurisdictional grid EF (0.977, 2014)

Safeguards

Grievance mechanism present; FPIC not stated; stakeholder co

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-30ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents