Xinjiang Muge Swine Farm Manure Management System GHG Mitigation Project
#184of 1084 in China#238of 1339 in Verra (VCS)#7of 66 in ACM0010
Audit Analysis
A VCS-registered swine manure management project (ACM0010) in Xinjiang, China, with VVB-confirmed additionality and quantified leakage, but a project-specific modeled baseline and multiple material findings in the verification report. The project delivered only about 26% of its pro-rata ex-ante expectation for the elapsed monitoring period, indicating conservative crediting. Low extraction confidence and several unquantified parameters (FNRB, usage monitoring, CORSIA/CCP status) limit the depth of assurance.
Red Flags
- The PDD (Nov 2022) states a lifetime ex-ante estimate of 2,908,811 tCO2e, while the verification report (Nov 2025) states 1,158,920 tCO2e — a 60% reduction that is not explained in the extracted record.
- Five corrective actions were raised in the verification report (SDG indicator alignment, default methane density, calibration schedule discrepancy, methane destruction data, government authorization evidence), indicating material gaps in the project's monitoring and documentation.
- FNRB value, usage monitoring method, and CORSIA/CCP eligibility are all not stated in the available documents, leaving key claim-safety parameters unverified.
- Min extraction confidence is rated low, meaning at least one key document was poorly readable, reducing assurance in the extracted data.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2021 | 13,678 | 0 | 13,678 | |
| Total | 13,678 | 0 | 13,678 |
Risk Indicators
VVB-confirmed combined test
Avoidance project, no reversal risk
Quantified at 16,555 tCO2e
Project-specific, modeled; reassessment not yet due
FPIC and grievance present; benefit sharing contradicted
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →